32451 Project Management For Gourmet Assessment Answer

As the Project Manager, you must now develop the project plan to present the detailed parameters of the project for signoff by the Project Sponsor and Executive Team of Alexander’s Deli. If these detailed parameters of the project are accepted, then the project may proceed to the project execution phase. 

Answer:

Project Background

Alexandria’s Gourmet Food was founded in 1992 with a retail food store in Australia, since then it could expand the business throughout the Australia. In merely two years started its own mail delivery of items at the doorstep and then slowly and slowly it continued to progress, and currently, it has 100 franchise business all over the country. Now the company with a view to expanding its base further has conceptualized to move from traditional business concept to on-line system. The company has visioned to expand business and customer base by allowing customers to book the food from the long list of items available in their shop and pay to confirm the order. In this manner, they will secure the payment before delivery. Now once the payment is done, then the delivery boy shall go and deliver the delicious food product at the doorstep. This can definitely add more customer satisfaction level and the increase in revenue generation. So with this point of view, all the board executives of Alexandria’s Gourmet Food have agreed principally for the project and the Project Charter is also approved.

The project ‘Gourmet Online’ is all about developing such an online system by which the Alexandria’s Gourmet Food can deliver the food to more customers with the ease of booking from their own place of comfort and get the doorstep delivery. Moreover, the company has a back office support team, who works mainly for the maintenance of the accounting system, shortlisting and selection of the new franchisee, recruitment of staffs, help in setting up the new stores for the new franchisees, managing the inventory for the supplied materials and consumables, warehouse functions and all IT related operations which are required to be interfaced with the newly developed system for an integrated approach to operation. So the new project needs to support these functions along with the log-in system for all new customers. The author shall act as the Project Manager of the said project and the software for the project shall be developed by ‘Sharp Software’ and the hardware required for the new project shall be procured using the normal contract procedure of request for quotations and according to the lowest bid, the hardware shall be selected. Providing the hardware, proper infrastructure and the high-security system to prevent it from any kind of cyber-attack is the full responsibility of the hardware supplier. All these terms are required to be covered well in the ‘Request for Proposal’ document from the beginning itself to avoid any kind of extra work or change order during the project phase. Since the purpose of RFP document in contract management is the first step which we are required to take to make our requirement clear to the probable supplier, the clarity in the RFP document needs to be maintained (Porter-Roth, 2002). And finally, for the testing of the system around 150 randomly selected customers along with some of the franchise centres shall also be used to assess the outcome of the project.

Project Goals or Objectives

The goals of the “Gourmet-Online” project are to:

  1. Improve customer satisfaction and hence customer retention,
  2. Obtain cost savings from more efficient order entry, enquiry and account payment processes
  3. Obtain cost savings from improved inventory, warehouse and supplier management processes
  4. Achieve significant staff productivity improvements

Project Stakeholders

Internal Stakeholder (The Denver Foundation, 2017):

Name

Role

Contact Details

Joanne Davis

CEO of Alexandria’s Gourmet Food

Project Sponsor

CIO of Alexandria’s Gourmet Food

Student’s Name

Project Manager of Gourmet Online Project

 

William Johnnie

Committee member of Franchise Owners

Dino Martin

Head of IT

Operations

Sheikh Mohammad

Head of Logistic Department

Shatakshi B.

Finance Team Member

Grihit B.

Sales and Marketing Member

Sonu Nigam

Customer service executive

External Stakeholder (Surbhi, 2015):

Name

Role

Contact Details

Anjan Dey

Sharp Software Project Coordinator

The Project’s MOV Statement

The areas of impact (Clarkson, 2012):

Rank 1

Financial

By introducing the new project, the customer service will definitely improve and so the customer base will definitely increase, and it will have positive impact on the Alexandria’s Gourmet Food’s financial results

Rank 2

Customer

This new ‘Gourmet Online’ project will definitely help in increasing the customer base and the business

Rank 3

Strategic

This project will improve the strategic association with more franchise owners and their base

Rank 4

Operational

The operation of the financial accounting system, recruitment of new franchise owners, expansion of shop base will become easy than now

Rank 5

Social

This will improve the social status of the organization and help in enhancing the standard

Value of this Project (Value Based Management, 2016):

Do more

This new project will definitely help the organization to expand and do more business and earn more revenues

Better

This project by integrating some of the back office features, this will provide better service to the customers and easy to order and pay for the selected food item

Faster

New proposed system will provide access to multiple customers at the same time and will help in booking food items more quickly and avoid to be in queue, so the all over system will become faster

Metrics with time frame:

Replace the existing system of inventory management & supplier management system with the new and advanced automatic repeat order system on the basis of stock availability

From 01/July/2018 onwards

Addition of 25 new franchisee stores after the implementation of the project ‘Gourmet Online’

By 31/December /2020 (18 months from the project implementation date)

Increase in volume of customers (at least 75%)

By 31/December /2020 (18 months from the project implementation date)

100% customer retention (existing), by improving the operation of system and providing the real-time price of all food products

From 01/July/2018 onwards

Start providing service 24 X 7 throughout the year

From 01/July/2018 onwards

Transaction rate will double from the current’s rate

By 31/December /2020 (18 months from the project implementation date)

MOV Statement (Clarkson, 2012):

The project ‘Gourmet Online’ shall be declared successful if the customers can log-in in the new system from 01/July/2018 onwards and be able to avail all the facilities as designed. Moreover, the increase in customer base can be declared successful if it increases by 75% from the existing and doubles the daily rate of transactions from the end of 2020 onwards. The success rate can be obtained if the continuous round the clock service could be provided to the customers from 01/July/2018.

Project Constraints

The constraints of the “Gourmet-Online” project are:

The completion date of June, 30th 2018
The budget of $A 6 million
The project team makeup has been determined and is 7 full-time members and 2 part-time members as follows:
Project Manager (1) - Full-time
Business Analysts (2) - Full-time
Hardware Engineer (2) - Full-time
Security Engineer (1) - Full-time
Network Engineer (1) - Full-time
Accountant (1) – Part-time
Vendor Relationship Manager (1) – Part-time 

Project Scope

The scope (Piscopo, 2017) of the project can be defined as the developing of the software system which is required for delivering the above-stated deliverables. The product-oriented scopes which shall be delivered are as below:

User registration: it shall be required to be done by the first time user or customer to register and document their address and phone number for the delivery of the food item, so that future promotional messages can be forwarded

Guest feature: this feature shall also provide the customer to book their order and pay online without doing registration and place order as a guest.

User-friendly: the system needs to be delivered user-friendly and the customers shall find the system very easy to book their choice online and get delivery at the doorstep.

Updated Status available: the status of the staff, food available on the basis of staff availability in each franchisee stores, real-time rates of the food items, approximate time of delivery at doorstep can be seen using the app or the system websites.

Large Database: it is required to be maintained for storing the data of all the customers and stores and their details for easy access and payment for the ordered food item.

High-security system: the newly developed system needs to be highly secured to prevent from any cyber-attack and malfunctioning to avoid customer’s dissatisfaction. Using the new system, the customer shall be able to make online payments for easy and

IT Architectural Plan: in the new system the user shall use the platform to place the order by selecting the food from the online available options, then the payment window will open up where the customer may choose to save the payment option or without saving the option they can go to checkout and pay the amount. Once the payment is received, the confirmation email with the expected time of delivery shall reach to the customer and the nearest available franchisee store will receive the order details and need to deliver the food item at doorstep before the provided time of delivery.

RFP process: the supply and integration of hardware required for the system, the infrastructure for the system and the security features of the system shall be selected on the basis of the traditional contractual type of floating the request for proposal document. Accordingly, the interested vendors shall provide the proposals with technical and commercial bids. After the bids are received, the Project Manager shall evaluate, negotiate and place the order to the selected vendor. The vendor needs to supply and integrate the hardware, infrastructure and security system of the software with the present back office facilities.

Requirements from the software: the software shall be developed by ‘Sharp Software’ and all the required features to provide customer satisfaction like the real-time rates, updates product list, balance time to deliver, payment received notification all such features are required to be designed by the Sharp Software for the Gourmet Online system.

Design and purchase of database as per the requirements: the database needs to be large enough with a huge data storage capacity to enable the storing of information related to all the individual log-in IDs, customers, bank details, franchisee’s details, payment details and other business details for the smooth performance of online transactions. So while designing the database, all the above considerations are required to be taken as the scope of developing the database. The database should be designed in a manner which can work with the existing system cohesively.

Outsourcing of the software development: the software required to develop the system and provide the desired facilities to the customers and Alexandria’s Gourmet Food franchisee owners and the store staffs to enable doing the business with ease and never face any black-out issues. The development work for such software is required to be outsourced due to non-availability of in-house staff that can fulfil such a high skill requirement. So the decision of outsourcing is advisable, but all the contractual terms and conditions are required to be finalized well with the Sharp Software to deliver the desired software on time, within the budgeted cost and the desired quality parameters and the maintenance of the developed system for the future use. So the Sharp Software shall be made responsible for the designing and developing the software along with the maintenance of the whole system after the implementation stage.

The Pilot test is required to be done: conducting the pilot tests after the designing and development of the system shall be covered under the scope of this project. During the test around 150 customers shall be selected on random basis along with few franchisee stores and the head office of the Alexandria’s Gourmet Food at NSW. The test is to be conducted to note the performance of the integrated system with the customer’s satisfaction level, ease of accepting the orders and delivering the food and back office activities shall be measured. In case of any finding, the system shall be reconfigured to fir the system requirement as per feedback.

Training needs identification and providing the training to the staffs: the training shall also be provided to the users and the franchisee staffs to use the system for providing the effective result.

Implementation of the system: after the designing and development of the system and the software is successfully pilot tested among the randomly selected customers and franchisee store it shall be now implemented throughout the Alexandria’s Gourmet Food stores. The designed web page shall be published online for the registration of the customers.

Back office system integration with the new system: the back office database system which conducts the finalisation of the new franchisee store, do all the marketing campaigning, then setting up a new store, all the required accounting systems, inventory management system, supplier management system, warehouse management system and other IT related system shall be synchronised with the project ‘Gourmet Online’.

Migration of data between both the systems: the scope of the project ‘Gourmet Online’ also includes the data migration from the traditional system to this new system.

Software development contract with Sharp Software: the software development contract shall be provided to Sharp Software on the basis of Design, Develop and Maintenance of the system. Even though the Sharp Software is well known and pre-booked vendor, but still the contract shall be finalized with all above terms and conditions. 

Task List

Scope Item: Developing the IT Architectural Plan

Task Name

Deliverable

Prepare the Hardware architectural plan

IT Architectural Plan

Prepare the Software architectural plan

 

Prepare the Security architectural plan

 

Prepare the Network architectural plan

 

Prepare the Database architectural plan

 

 

Scope Item: Develop the Scope Management Plan

Task Name

Deliverable

Prepare the Scope Management Plan

Scope Management Plan

Organize meetings to identify the requirements

 

Finalize the requirement of the Project

 

Define the Scope of the Project

 

Prepare the WBS to further divide the overall scope of the project

 

 

Scope Item: Develop the Time Management Plan

Task Name

Deliverable

Prepare the Schedule Management Plan

Level III Schedule of the project & Time Management Plan

Define the activities of the Project

 

Sequence the activities of the project

 

Estimate the resources required for completing the activities

 

Estimate the duration of the activities

 

 

Scope Item: Develop the Cost Management Plan

Task Name

Deliverable

Prepare the Cost Management plan

Project Budget Estimate

Estimate the cost of the project

 

Prepare the Budget

 

 

Scope Item: Develop the Risk Management Plan

Task Name

Deliverable

Prepare the Risk Management Plan

Updated Risk Register

Prepare the Risk Register with all threats & opportunities

 

Develop the Qualitative Analysis of the risks

 

Develop the Quantitative Analysis of the risks

 

Develop the Risk Response Plan of the identified risks

 

 

Scope Item: Develop the other required PM documents

Task Name

Deliverable

Prepare the Communication Plan for managing the Stakeholders

Communication Management Plan

Prepare the Contract Management Plan for placing orders to Sharp Software & hardware

Contract Management Plan

Prepare the Human Resource Management Plan

HR Management Plan

 

Scope Item: Human Resource Recruitment

Task Name

Deliverable

Publish advertisement

Provide the appointment letter to the selected team members

Receive the resumes

 

Analyse and shortlist the resumes according to their experience in similar project

 

Conduct interview

 

Negotiate & Select the candidates

 

 

Scope Item: Place Contract for Hardware, infrastructure and Security system

Task Name

Deliverable

Prepare the Request for Proposal (RFP) document

Issue Purchase Order to selected vendor for the design, develop and implement the system

Float the RFP document through Newspaper and Social media

 

Receive the proposals (Bids)

 

Evaluate the bids received

 

Shortlist the bidders & Negotiate with them

 

Finalize the bidder

 

 

Scope Item: Place contract for Software development & maintenance of the system to Sharp Software

Task Name

Deliverable

Negotiate terms with Sharp Software

Issuance of Contract to Sharp Software

Issue the Service Order request letter

 

 

Scope Item: Design the Software

Task Name

Deliverable

Define the output of the software requirement

Designing of the Software

Define the data flow

 

Develop the logic to get the desired output

 

Document the Program

 

 

Scope Item: Design the Database

Task Name

Deliverable

Determine the entities/tables required to be included

Complete the designing of database

Determine the attributes/fields required to be included

 

Identify & document the unique fields required

 

Set the relationships between tables

 

Normalize the design

 

Enter all the raw data

 

 

Scope Item: Design the security features

Task Name

Deliverable

Define the required level of security feature

Designing of security features

Design & Select the LAN / WLAN for providing a security protective information

 

Design the proper tools like Firewalls to protect the system

 

 

Scope Item: Purchase & procure the Hardware

Task Name

Deliverable

Place order to the sub-vendors

Deliver the Hardware system at Head Office, NSW

Receive product from sub-vendors

 

Assemble all received parts from sub-vendors

 

Test the assembled hardware system

 

Dispatch & Deliver the Hardware

 

 

Scope Item: Purchase & procure the  IT infrastructure

Task Name

Deliverable

Place order to the sub-vendors

Deliver the IT Infrastructure system at Head Office, NSW

Receive product from sub-vendors

 

Assemble all received parts from sub-vendors

 

Test the assembled IT Infrastructure system

 

Dispatch & Deliver the IT Infrastructure

 

 

Scope Item: Purchase & procure the  Security system

Task Name

Deliverable

Procure LAN / WLAN for providing a security protective information

Deliver the Security system at Head Office, NSW

Procure proper tools like Firewalls to protect the system

 

Conduct preliminary test

 

 

Scope Item: Purchase the Database

Task Name

Deliverable

Finalise the tables with raw data to suit the requirement of new system

Deliver the database at Head Office, NSW

Obtain approval on the type of database developed

 

 

Scope Item: Develop the System

Task Name

Deliverable

Development of Software

Development of the whole new system

Manage to obtain the integrity between client, server and the network system

 

Develop the proper Security system

 

Set up the IT Infrastructure

 

Set up the Hardware systems

 

 

Scope Item: Conduct Pilot Test

Task Name

Deliverable

Prepare the procedure to conduct pilot test

Complete conducting the pilot test

Obtain approval of procedure to conduct pilot test

 

Select 150 customers randomly

 

Select randomly franchisee store

 

Conduct the pilot test

 

 

Scope Item: Implement the system

Task Name

Deliverable

Implement the Hardware

Complete implementation of the new system

Implement the IT Infrastructure

 

Implement the Security System

 

Implement the software

 

Implement the Database

 

 

Scope Item: Integration with the back office system at NSW

Task Name

Deliverable

Configure the old system as per the new system's requirement

Integration of the old & new system

Integrate the New system with the old one

 

 

Scope Item: Migration of the data from the old to new system

Task Name

Deliverable

Develop the database system to accommodate the old data

Complete the migration of old to new system

Transfer the data from old system to the new one

 

 

Scope Item: Train the Staffs

Task Name

Deliverable

Prepare training manuals

Complete providing training to all staffs

Obtain approval on the developed training manual

 

Provide training to the users / franchise store's staffs

 

 

Scope Item: Closing & Evaluation of Gourmet Online Food Project

Task Name

Deliverable

Document the lessons learned

Completion of Gourmet Online Food Project

Evaluate the project outcomes

 

Document the project outcomes

 

Project Budget

Sl. No.

Component (McConnell, 2011)

Estimated Cost
(multiple of $ 25,000)

1

Outsourced “Gourmet-Online” Software Development

 

1.1

Service contract to Sharp Software

24.00

2

Gourmet-Online Software Implementation

12.00

3

Training (Alexandria’s Gourmet Food Corporate staff and Franchise Operators)

12.00

4

Hardware, network infrastructure and security components (RFP, purchase & implementation)

 

4.1

Common RFP process for all the three items

14.40

4.2

Purchase and Implementation of Hardware

31.20

4.3

Purchase and Implementation of IT Infrastructure

31.20

4.4

Purchase and Implementation of Security Components

31.20

5

Database (purchase & implementation)

 

5.1

Purchase Database

19.20

5.2

Implementation of Database

4.80

6

Migration of required existing Business Data

12.00

7

Project staff costs (Alexandria’s Corporate staff only)

 

7.1

Project Manager (Full-time – 1 No.)

3.67

7.2

Business Analysts - Full-time – 2 Nos.

6.67

7.3

Hardware Engineer (Full-time – 2 Nos.)

6.00

7.4

Security Engineer (Full-time – 1 No.)

2.33

7.5

Network Engineer (Full-time – 1 No.)

2.83

7.6

Accountant (Part-time – 1 No.)

0.83

7.7

Vendor Relationship Manager (Part-time – 1 No.)

1.67

 

Sub Total

 

8

Contingency @ 10% of Total

24.00

 

Total

240

Project Time Estimate

WBS

Task Name (Harrin, 2017)

Duration

Start

Finish

1

Gourmet Online Food Project

195 days

Mon 10/2/17

Fri 6/29/18

1.1

   Planning activities for developing Gourmet Online Food Project

72 days

Mon 10/2/17

Tue 1/9/18

1.1.1

      Developing the IT Architectural Plan

21 days

Mon 10/2/17

Mon 10/30/17

1.1.1.1

         Deliverable: Project Charter approval obtained

0 days

Mon 10/2/17

Mon 10/2/17

1.1.1.2

         Prepare the Hardware architectural plan

5 days

Mon 10/2/17

Fri 10/6/17

1.1.1.3

         Prepare the Software architectural plan

5 days

Mon 10/9/17

Fri 10/13/17

1.1.1.4

         Prepare the Security architectural plan

3 days

Mon 10/16/17

Wed 10/18/17

1.1.1.5

         Prepare the Network architectural plan

5 days

Thu 10/19/17

Wed 10/25/17

1.1.1.6

         Prepare the Database architectural plan

3 days

Thu 10/26/17

Mon 10/30/17

1.1.1.7

         Deliverable: IT Architectural Plan

0 days

Mon 10/30/17

Mon 10/30/17

1.1.2

      Develop the Scope Management Plan

14 days

Tue 10/31/17

Fri 11/17/17

1.1.2.1

         Prepare the Scope Management Plan

4 days

Tue 10/31/17

Fri 11/3/17

1.1.2.2

         Organize meetings to identify the requirements

4 days

Mon 11/6/17

Thu 11/9/17

1.1.2.3

         Finalize the requirement of the Project

4 days

Wed 11/8/17

Mon 11/13/17

1.1.2.4

         Define the Scope of the Project

2 days

Tue 11/14/17

Wed 11/15/17

1.1.2.5

         Prepare the WBS to further divide the overall scope of the project

2 days

Thu 11/16/17

Fri 11/17/17

1.1.2.6

         Deliverable: Scope Management Plan

0 days

Fri 11/17/17

Fri 11/17/17

1.1.3

      Develop the Time Management Plan

14 days

Mon 11/20/17

Thu 12/7/17

1.1.3.1

         Prepare the Schedule Management Plan

3 days

Mon 11/20/17

Wed 11/22/17

1.1.3.2

         Define the activities of the Project

4 days

Thu 11/23/17

Tue 11/28/17

1.1.3.3

         Sequence the activities of the project

2 days

Wed 11/29/17

Thu 11/30/17

1.1.3.4

         Estimate the resources required for completing the activities

4 days

Wed 11/29/17

Mon 12/4/17

1.1.3.5

         Estimate the duration of the activities

3 days

Tue 12/5/17

Thu 12/7/17

1.1.3.6

         Deliverable: Level III Schedule of the project & Time Management Plan

0 days

Thu 12/7/17

Thu 12/7/17

1.1.4

      Develop the Cost Management Plan

9 days

Tue 12/5/17

Fri 12/15/17

1.1.4.1

         Prepare the Cost Management plan

3 days

Tue 12/5/17

Thu 12/7/17

1.1.4.2

         Estimate the cost of the project

4 days

Fri 12/8/17

Wed 12/13/17

1.1.4.3

         Prepare the Budget

2 days

Thu 12/14/17

Fri 12/15/17

1.1.4.4

         Deliverable: Project Budget Estimate

0 days

Fri 12/15/17

Fri 12/15/17

1.1.5

      Develop the Risk Management Plan

18 days

Fri 12/8/17

Tue 1/2/18

1.1.5.1

         Prepare the Risk Management Plan

3 days

Fri 12/8/17

Tue 12/12/17

1.1.5.2

         Prepare the Risk Register with all threats & opportunities

5 days

Mon 12/18/17

Fri 12/22/17

1.1.5.3

         Develop the Qualitative Analysis of the risks

1 day

Mon 12/25/17

Mon 12/25/17

1.1.5.4

         Develop the Quantitative Analysis of the risks

3 days

Tue 12/26/17

Thu 12/28/17

1.1.5.5

         Develop the Risk Response Plan of the identified risks

3 days

Fri 12/29/17

Tue 1/2/18

1.1.5.6

         Deliverable: Updated Risk Register

0 days

Tue 1/2/18

Tue 1/2/18

1.1.6

      Develop the other required PM documents

37 days

Mon 11/20/17

Tue 1/9/18

1.1.6.1

         Prepare the Communication Plan for managing the Stakeholders

7 days

Mon 12/25/17

Tue 1/2/18

1.1.6.2

         Prepare the Contract Management Plan for placing orders to Sharp Software & hardware

10 days

Mon 11/20/17

Fri 12/1/17

1.1.6.3

         Prepare the Human Resource Management Plan

5 days

Wed 1/3/18

Tue 1/9/18

1.1.6.4

         Deliverable: Contract Management Plan

0 days

Fri 12/1/17

Fri 12/1/17

1.1.6.5

         Deliverable: Communication Management Plan

0 days

Tue 1/2/18

Tue 1/2/18

1.1.6.6

         Deliverable: HR Management Plan

0 days

Tue 1/9/18

Tue 1/9/18

1.2

   Execution, Monitoring & Control the Gourmet Online Food Project

143 days

Mon 12/4/17

Wed 6/20/18

1.2.1

      Human Resource Recruitment

22 days

Wed 1/10/18

Thu 2/8/18

1.2.1.1

         Publish advertisement

3 days

Wed 1/10/18

Fri 1/12/18

1.2.1.2

         Receive the resumes

10 days

Mon 1/15/18

Fri 1/26/18

1.2.1.3

         Analyze and shortlist the resumes according to their experience in similar project

2 days

Mon 1/29/18

Tue 1/30/18

1.2.1.4

         Conduct interview

5 days

Wed 1/31/18

Tue 2/6/18

1.2.1.5

         Negotiate & Select the candidates

2 days

Wed 2/7/18

Thu 2/8/18

1.2.1.6

         Deliverable: Provide the appointment letter to the selected team members

0 days

Thu 2/8/18

Thu 2/8/18

1.2.2

      Contract Placement

80 days

Mon 12/4/17

Fri 3/23/18

1.2.2.1

         Place Contract for Hardware, infrastructure and Security system

31 days

Fri 2/9/18

Fri 3/23/18

1.2.2.1.1

            Prepare the Request for Proposal (RFP) document

3 days

Fri 2/9/18

Tue 2/13/18

1.2.2.1.2

            Float the RFP document through Newspaper and Social media

1 day

Wed 2/14/18

Wed 2/14/18

1.2.2.1.3

            Receive the proposals (Bids)

15 days

Thu 2/15/18

Wed 3/7/18

1.2.2.1.4

            Evaluate the bids received

4 days

Thu 3/8/18

Tue 3/13/18

1.2.2.1.5

            Shortlist the bidders & Negotiate with them

1 day

Tue 3/20/18

Tue 3/20/18

1.2.2.1.6

            Finalize the bidder

3 days

Wed 3/21/18

Fri 3/23/18

1.2.2.1.7

            Deliverable: Issue Purchase Order to selected vendor for the design, develop and implement the system

0 days

Fri 3/23/18

Fri 3/23/18

1.2.2.2

         Place contract for Software development & maintenance of the system to Sharp Software

7 days

Mon 12/4/17

Tue 12/12/17

1.2.2.2.1

            Negotiate terms with Sharp Software

5 days

Mon 12/4/17

Fri 12/8/17

1.2.2.2.2

            Issue the Service Order request letter

2 days

Mon 12/11/17

Tue 12/12/17

1.2.2.2.3

            Deliverable: Issuance of Contract to Sharp Software

0 days

Tue 12/12/17

Tue 12/12/17

1.2.3

      Design the System

92 days

Wed 12/13/17

Thu 4/19/18

1.2.3.1

         Design the Software

25 days

Wed 12/13/17

Tue 1/16/18

1.2.3.1.1

            Define the output of the software requirement

2 days

Wed 12/13/17

Thu 12/14/17

1.2.3.1.2

            Define the data flow

3 days

Fri 12/15/17

Tue 12/19/17

1.2.3.1.3

            Develop the logic to get the desired output

15 days

Wed 12/20/17

Tue 1/9/18

1.2.3.1.4

            Document the Program

5 days

Wed 1/10/18

Tue 1/16/18

1.2.3.1.5

            Deliverable: designing of the Software

0 days

Tue 1/16/18

Tue 1/16/18

1.2.3.2

         Design the Database

19 days

Mon 3/26/18

Thu 4/19/18

1.2.3.2.1

            Determine the entities/tables required to be included

4 days

Mon 3/26/18

Thu 3/29/18

1.2.3.2.2

            Determine the attributes/fields required to be included

5 days

Mon 3/26/18

Fri 3/30/18

1.2.3.2.3

            Identify & document the unique fields required

3 days

Mon 4/2/18

Wed 4/4/18

1.2.3.2.4

            Set the relationships between tables

4 days

Thu 4/5/18

Tue 4/10/18

1.2.3.2.5

            Normalize the design

2 days

Wed 4/11/18

Thu 4/12/18

1.2.3.2.6

            Enter all the raw data

5 days

Fri 4/13/18

Thu 4/19/18

1.2.3.2.7

            Deliverable: complete the designing of database

0 days

Thu 4/19/18

Thu 4/19/18

1.2.3.3

         Design the security features

12 days

Mon 3/26/18

Tue 4/10/18

1.2.3.3.1

            Define the required level of security feature

2 days

Mon 3/26/18

Tue 3/27/18

1.2.3.3.2

            Design & Select the LAN / WLAN for providing a security protective information

10 days

Wed 3/28/18

Tue 4/10/18

1.2.3.3.3

            Design the proper tools like Firewalls to protect the system

10 days

Wed 3/28/18

Tue 4/10/18

1.2.3.3.4

            Deliverable: Designing of security features

0 days

Tue 4/10/18

Tue 4/10/18

1.2.4

      Purchase and Procure

46 days

Thu 3/8/18

Thu 5/10/18

1.2.4.1

         Purchase & procure the Hardware

42 days

Thu 3/8/18

Fri 5/4/18

1.2.4.1.1

            Place order to the sub-vendors

3 days

Mon 3/26/18

Wed 3/28/18

1.2.4.1.2

            Receive product from sub-vendors

20 days

Thu 3/8/18

Wed 4/4/18

1.2.4.1.3

            Assemble all received parts from sub-vendors

10 days

Thu 4/12/18

Wed 4/25/18

1.2.4.1.4

            Test the assembled hardware system

2 days

Thu 4/26/18

Fri 4/27/18

1.2.4.1.5

            Dispatch & Deliver the Hardware

5 days

Mon 4/30/18

Fri 5/4/18

1.2.4.1.6

            Deliverable: Deliver the Hardware system at Head Office, NSW

0 days

Fri 5/4/18

Fri 5/4/18

1.2.4.2

         Purchase & procure the IT infrastructure

36 days

Thu 3/15/18

Thu 5/3/18

1.2.4.2.1

            Place order to the sub-vendors

3 days

Mon 3/26/18

Wed 3/28/18

1.2.4.2.2

            Receive product from sub-vendors

15 days

Thu 3/15/18

Wed 4/4/18

1.2.4.2.3

            Assemble all received parts from sub-vendors

5 days

Thu 4/19/18

Wed 4/25/18

1.2.4.2.4

            Test the assembled IT Infrastructure system

1 day

Thu 4/26/18

Thu 4/26/18

1.2.4.2.5

            Dispatch & Deliver the IT Infrastructure

5 days

Fri 4/27/18

Thu 5/3/18

1.2.4.2.6

            Deliverable: Deliver the IT Infrastructure system at Head Office, NSW

0 days

Thu 5/3/18

Thu 5/3/18

1.2.4.3

         Purchase & procure the Security system

22 days

Wed 4/11/18

Thu 5/10/18

1.2.4.3.1

            Procure LAN / WLAN for providing a security protective information

20 days

Wed 4/11/18

Tue 5/8/18

1.2.4.3.2

            Procure proper tools like Firewalls to protect the system

10 days

Wed 4/25/18

Tue 5/8/18

1.2.4.3.3

            Conduct preliminary test

2 days

Wed 5/9/18

Thu 5/10/18

1.2.4.3.4

            Deliverable: Deliver the Security system at Head Office, NSW

0 days

Thu 5/10/18

Thu 5/10/18

1.2.4.4

         Purchase the Database

7 days

Fri 4/20/18

Mon 4/30/18

1.2.4.4.1

            Finalise the tables with raw data to suit the requirement of new system

5 days

Fri 4/20/18

Thu 4/26/18

1.2.4.4.2

            Obtain approval on the type of database developed

2 days

Fri 4/27/18

Mon 4/30/18

1.2.4.4.3

            Deliverable: Deliver the database at Head Office, NSW

0 days

Mon 4/30/18

Mon 4/30/18

1.2.5

      Develop the System

87 days

Wed 1/17/18

Thu 5/17/18

1.2.5.1

         Development of Software

5 days

Wed 1/17/18

Tue 1/23/18

1.2.5.2

         Manage to obtain the integrity between client, server and the network system

3 days

Wed 1/24/18

Fri 1/26/18

1.2.5.3

         Develop the proper Security system

5 days

Fri 5/11/18

Thu 5/17/18

1.2.5.4

         Set up the IT Infrastructure

10 days

Fri 5/4/18

Thu 5/17/18

1.2.5.5

         Set up the Hardware systems

3 days

Mon 5/7/18

Wed 5/9/18

1.2.5.6

         Deliverable: Development of the whole new system

0 days

Thu 5/17/18

Thu 5/17/18

1.2.6

      Conduct Pilot Test

19 days

Fri 4/20/18

Wed 5/16/18

1.2.6.1

         Prepare the procedure to conduct pilot test

10 days

Fri 4/20/18

Thu 5/3/18

1.2.6.2

         Obtain approval of procedure to conduct pilot test

2 days

Fri 5/4/18

Mon 5/7/18

1.2.6.3

         Select 150 customers randomly

2 days

Tue 5/8/18

Wed 5/9/18

1.2.6.4

         Select randomly franchisee store

1 day

Tue 5/8/18

Tue 5/8/18

1.2.6.5

         Conduct the pilot test

5 days

Thu 5/10/18

Wed 5/16/18

1.2.6.6

         Deliverable: Complete conducting the pilot test

0 days

Wed 5/16/18

Wed 5/16/18

1.2.7

      Implement the system

22 days

Tue 5/1/18

Wed 5/30/18

1.2.7.1

         Implement the Hardware

3 days

Thu 5/17/18

Mon 5/21/18

1.2.7.2

         Implement the IT Infrastructure

10 days

Thu 5/17/18

Wed 5/30/18

1.2.7.3

         Implement the Security System

3 days

Thu 5/17/18

Mon 5/21/18

1.2.7.4

         Implement the software

3 days

Thu 5/17/18

Mon 5/21/18

1.2.7.5

         Implement the Database

3 days

Tue 5/1/18

Thu 5/3/18

1.2.7.6

         Deliverable: Complete implementation of the new system

0 days

Wed 5/30/18

Wed 5/30/18

1.2.8

      Integration with the back office system at NSW

15 days

Thu 5/17/18

Wed 6/6/18

1.2.8.1

         Configure the old system as per the new system's requirement

10 days

Thu 5/17/18

Wed 5/30/18

1.2.8.2

         Integrate the New system with the old one

5 days

Thu 5/31/18

Wed 6/6/18

1.2.8.3

         Deliverable: Integration of the old & new system

0 days

Wed 6/6/18

Wed 6/6/18

1.2.9

      Migration of the data from the old to new system

20 days

Thu 5/17/18

Wed 6/13/18

1.2.9.1

         Develop the database system to accommodate the old data

10 days

Thu 5/17/18

Wed 5/30/18

1.2.9.2

         Transfer the data from old system to the new one

5 days

Thu 6/7/18

Wed 6/13/18

1.2.9.3

         Deliverable: Complete the migration of old to new system

0 days

Wed 6/13/18

Wed 6/13/18

1.2.10

      Train the Staffs

24 days

Fri 5/18/18

Wed 6/20/18

1.2.10.1

         Prepare training manuals

15 days

Fri 5/18/18

Thu 6/7/18

1.2.10.2

         Obtain approval on the developed training manual

2 days

Fri 6/8/18

Mon 6/11/18

1.2.10.3

         Provide training to the users / franchise store's staffs

5 days

Thu 6/14/18

Wed 6/20/18

1.2.10.4

         Deliverable: complete providing training to all staffs

0 days

Wed 6/20/18

Wed 6/20/18

1.3

   Closing & Evaluation of Gourmet Online Food Project

7 days

Thu 6/21/18

Fri 6/29/18

1.3.1

      Document the lessons learned

5 days

Thu 6/21/18

Wed 6/27/18

1.3.2

      Evaluate the project outcomes

5 days

Thu 6/21/18

Wed 6/27/18

1.3.3

      Document the project outcomes

2 days

Thu 6/28/18

Fri 6/29/18

1.3.4

      Deliverable: Completion of Gourmet Online Food Project

0 days

Fri 6/29/18

Fri 6/29/18

Quality Management Process

This process will ensure the delivery of the product (the online system) within the budgeted time, cost and adhering to the provided quality standards (Method 123, 2017). The basic steps of conducting the quality management are:

Perform Quality Assurance: the project team need to always keep on tracking the quality standards with respect to the planning figures

Do Quality Control: any audit findings need to be addressed immediately and to monitor and control the quality of the project and product

Always adopt for Quality Improvement: the philosophy of continuous quality improvement is to be adopted by the project team members and all efforts are needed to be undertaken the team members

Implement the approved method of Quality Management: in every PDCA cycle the outcome improvement method is required to be approved by the sponsor before applying in the whole project and the same process needs to be repeated till the completion of the project. 

Risk Management Process

Risk Identification (OneCampus, 2017): This is the first step, where the team member and the other stakeholders shall identify the various threats and opportunities of the project

Conduct Qualitative Analysis: after the lists of risks are identified, they are to be analysed according to its probability of happening and the impact on the project if it happens.

Conduct Quantitative Analysis: there are various tools and techniques which can be used to calculate the cost of the risk if it happens.

Rank the risks: on the basis of cost, the risks are arranged in descending value of risks with the maximum amount risk at the top and the minimum at below most rows.

Plan response or mitigation (Sciences Engineering Medicine, 2017): once the identification and analysis are done, the mitigation plan either ‘accept’, ‘reduce’, ‘mitigate’, ‘enhance’ in case of opportunity etc. are used and the best option is adopted.

Project Monitoring and Control

Meetings: there shall be the weekly meeting between the team members and monthly once with the Project Sponsor.

Reports: the cost, progress, quality and change order status shall be pushed via e-mail and presented at the weekly meeting. During the monthly meeting with sponsor and vendors, trend analysis, progress status, concern status, backlog analysis in case of delays and catch-up plan is to be presented.

Project Control Structure: the Project Manager shall lead the project control job for the project. In project control, the Project Manager shall always keep on doing checks and analysis to complete the project within budgeted time and cost (Aramyan, 2016).

Change Control Process (Carman, 2013): any kind of change in the project which can impact the time, cost and quality of the project shall be treated under this process. The changes need to be first assessed by the PM for the impact on time and cost of the project and then it is up to sponsor whether to accept the change or reject it. 

Implementation Strategy

Task (Edwards & Richards, 2014)

% Comp.

Status

Actual Start Date

Forecast Finish Date

Actual Finish Date

Owner of the Task

Priority

Approval of Project Charter

100%

Completed

20 Sep 2017

2 Oct 2017

2 Oct 2017

Project Sponsor

High

Planning activities

2%

In Progress

2 Oct 2017

9 Jan 2018

-

Project Manager

Medium

Recruit Project Team

0%

Not Started

10 Jan 2018

8 Feb 2018

-

Project Manager

High

Contract Placement

0%

Not Started

4 Dec 2017

23 Mar 2018

-

Project Team

High

Design the System

0%

Not Started

13 Dec 2017

19 Apr 2018

-

Vendors

Medium

Purchase and Procure

0%

Not Started

8 Mar 2018

10 May 2018

-

Vendors

High

Develop the System

0%

Not Started

17 Jan 2018

17 May 2018

-

Vendors

High

Conduct Pilot Test

0%

Not Started

20 Apr 2018

16 May 2018

-

Vendors

High

Implement the system

0%

Not Started

1 May 2018

30 May 2018

-

Vendors

Medium

Integration with the back office system at NSW

0%

Not Started

17 May 2018

6 Jun 2018

-

Vendors

Medium

Migration of the data from the old to new system

0%

Not Started

17 May 2018

13 Jun 2018

-

Vendors

Medium

Train the Staffs

0%

Not Started

18 May 2018

20 Jun 2018

-

Vendors

Low

Closing & Evaluation of Gourmet Online Food Project

0%

Not Started

21 Jun 2018

29 Jun 2018

-

Project Manager

Medium

Recommendations

It is recommended that as the ‘Project Charter’ is approved so the next step was developing the ‘Project Plan’ which is now developed. Once the document developed the Project Plan is approved then the Project Team can move to the next stage that is ‘Execution of Gourmet Online Food Project’. The time period available to complete the work is tight but achievable, even the cost too. So the Project Team need to be cautious about the quality of the product as well as the time and cost baseline too.

Approvals

This project plan has presented the detailed parameters of the “Gourmet Online Food Project”. Now after the acceptance and signed off of the parameters presented, the project is allowed to move to the execution phase.

_______________________________                  _________________________

(Signature)                                                    (Signature)

Executive Team                                              Joanne Davis, Project Manager 

References 

Aramyan, P., 2016. What are Project controls? Why are they so important in project management and how to deal with them! [Online] Logic Software, Inc. Available at: https://explore.easyprojects.net/blog/what-are-project-controls-why-are-they-so-important-in-project-management-and-how-to-deal-with-them [Accessed 11 October 2017].

Carman, C., 2013. 4 Steps to Effective Change Control. [Online] Dice Available at: https://insights.dice.com/2013/05/08/why-change-control-isnt-for-sissies/ [Accessed 11 October 2017].

Clarkson, A., 2012. IT Project Management | Measurable Organizational Value. [Online] Available at: https://classlessnotes.blogspot.in/2012/01/it-project-management-measurable.html [Accessed 11 October 2017].

Edwards, G. & Richards, F., 2014. Putting Together a Project Implementation Plan. [Online] Available at: https://www.brighthubpm.com/project-planning/87423-putting-together-a-project-implementation-plan/ [Accessed 11 October 2017].

Harrin, E., 2017. What Is Project Time Management? [Online] Available at: https://www.thebalance.com/what-is-project-time-management-3879177 [Accessed 11 October 2017].

McConnell, E., 2011. Project Budget and Financial Resources. [Online] Available at: https://www.mymanagementguide.com/project-budget-and-financial-resources/ [Accessed 11 October 2017].

Method 123, 2017. Quality Management Process. [Online] Palmetto Document Systems,Inc. Available at: https://www.method123.com/quality-management.php [Accessed 11 October 2017].

OneCampus, 2017. [Online] Available at: https://www.greycampus.com/opencampus/project-management-professional/plan-risk-responses [Accessed 11 October 2017].

Piscopo, M., 2017. Scope Management Plan. [Online] Available at: https://www.projectmanagementdocs.com/project-planning-templates/scope-management-plan.html#axzz4tfIbGW8q [Accessed 11 October 2017].

Porter-Roth, B., 2002. Request for Proposal: A Guide to Effective RFP Development. 1st ed. Addison-Wesley Professional.

Sciences Engineering Medicine, 2017. [Online] Available at: https://www.nap.edu/read/11183/chapter/7#51 [Accessed 11 October 2017].

Surbhi, S., 2015. Difference Between Internal and External Stakeholders. [Online] Available at: https://keydifferences.com/difference-between-internal-and-external-stakeholders.html [Accessed 11 October 2017].

The Denver Foundation, 2017. Identifying internal and external Stakeholders. [Online] Available at: https://www.nonprofitinclusiveness.org/identifying-internal-and-external-stakeholders [Accessed 11 October 2017].

Value Based Management, 2016. Agreeing on Roles and Responsibilities: Summary of RACI. [Online] Available at: https://www.valuebasedmanagement.net/methods_raci.html [Accessed 11 October 2017]. 


Buy 32451 Project Management For Gourmet Assessment Answers Online

Talk to our expert to get the help with 32451 Project Management For Gourmet Assessment Answers from Assignment Hippo Experts to complete your assessment on time and boost your grades now

The main aim/motive of the finance assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignment help Australia. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at www.assignmenthippo.com are so much skilled, capable, talented, and experienced in their field and use our best and free Citation Generator and cite your writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for 32451 Project Management For Gourmet Assessment Answer Assignment Help Online

Want to order fresh copy of the Sample 32451 Project Management For Gourmet Assessment Answers? online or do you need the old solutions for Sample 32451 Project Management For Gourmet Assessment Answer, contact our customer support or talk to us to get the answers of it.

Assignment Help Australia
Want latest solution of this assignment

Want to order fresh copy of the 32451 Project Management For Gourmet Assessment Answers? online or do you need the old solutions for Sample 32451 Project Management For Gourmet Assessment Answer, contact our customer support or talk to us to get the answers of it.