1. Develop a Charter for the project
2.Develop a comprehensive Project Plan that should meet implementation and training requirements
3. Both Charter and Project plan must be ratified (signed) by the Business Sponsor. Please note, no work could commence without formal ratification of the Charter and Project plan documents.
4.  Once the project is in progress, you are required to provide project status updates to your VUISC Manager (tutor), project team members and the business sponsor.

Answer:

Introduction

A project plan is to be prepared for yes chemist that manages a group of independent Pharmacies with a shared value and common philosophy. The business of yes Chemist Pty Ltd had started as a family venture in late 2010s, which has gradually expanded stores in all the major cities of Australia, which includes Sydney, Brisbane Adelaide, Perth and Melbourne.  The business of Yes Chemist has been doing well for quite a sometime and therefore, the organization has decided to implement SAP for integrating all the major business operations of the organization. The need of a new accounting, HR and inventory management system is essential as an operational review that was conducted resulted unveiled the weaknesses in the existing system (Schwalbe 2015). The Victoria University Information Systems Consulting mainly secured the contract for implementing the SA S/4HANA for SAP Business All in one.

The main purpose of this project plan is to define the scope of the project including the major project deliverables associated with the project and project quality standards. The quality standards requirement for the project will be discussed as well (Leach 2014). The project Plan outlines the business case for the project that justifies the need of the project. The project schedule and the approach of implementing the project are discussed in the project plan. The project plan further covers the resources, budget and risks associated with a project. A communication matrix is also prepared that includes different communication activities associated with the project. This project plan is prepared to get an overview of the different project activities, schedule and the deliverables. 

Project scope

The aim of the project is to implement SAP S/4HANA for SAP Business All in one for Yes chemist Pvt Ltd. The system development life cycle of the project mainly consists of the development, testing and the user acceptance testing as well. The system will be set up on cloud considering the fact that server room refurbishment will take almost three months to complete (Kerzner and Kerzner 2017). The project would be a success only if the hardware and the software installation are complete. The data conversion, which is an important project deliverable should be completed successfully. With the implementation of a new system, it is very essential to train the existing users of the organization about the use of the software in the organization (Harrison and Lock 2017). This process is followed by the user acceptance testing.

The objective of the project is to deliver the identified deliverables of the project on time. The project will be a success only if the major deliverables of the project manages to achieve the desired quality standards for the project. The deliverables and the quality standards required for the acceptance of each deliverables is represented in the following table (Burke 2013).

Deliverables

Acceptance Criteria of Quality Standards

Development of Infrastructure and Equipment

The work should be completed within 15 days as quoted by the contractor started from 3rd of June

Collection of the functional requirements of the new system design associated with the project

The requirement fetching should incorporate the all the functional requirements of the project.

Data Conversion is another major deliverable of the project. Since the company is integrating all their business processes in a new SAP instance, data extraction, conversion, validation and transitioning is essential. This data conversion will take at least 3 weeks.

The acceptance criteria of this deliverable will be conversion of data according to legacy data structure and proper identification and rectification of the defect in data conversion (if any).

Integration and Testing- Integration and testing is one of the most important deliverables of the project as the success of the project largely depends on the proper integration of the new SAP system will the e-gate feature for corporate banking associated with the organization.

The deliverable will be accepted only after a comprehensive end to end testing within All in one finance module. This should incorporate testing with a live e ate instance and postings in journal ledger.

Documentation of the project work

This deliverable will only be accepted if the documentation process is completed by a technical writer of VUISC. The documentation process should include review standard SAO business All in one end user manuals.

Training the users

Since VUISC is implementing the project, it is essential that the training is imparted by VUISC trainer only as this trainer will have a proper knowledge about the working process of the software.

Maintenance

The acceptance criterion is that a regular maintenance is ensured.  

The assumptions are-

  1. A realistic schedule is set
  2. The budget allocation is appropriate

The Constrains are as follows-

  1. Maintenance does not include disaster or data recovery and it is the responsibility of the client.
  2. The budget may not incorporate hike in the wages of the workers.

Business case

The business needs that the project is expected to address (Heagney 2016)-

  1. The Sap system will provide a solution to replace the legacy accounting, HR and inventory management system.
  2. The new SAP system is expected to mitigate the operational weaknesses associated with Yes Chemist.
  3. The process of data storage will be automated that will help in easier data extraction

The project is justified as with the increase in the business units of Yes Chemist, it is essential to upgrade the existing system to make the process of information storage and retrieval easier.

The expected benefits of the project is represented in the following table-

Benefits

Benefit Measures

Significant Cost savings

The SAP software is capable of tracking the company’s data and generates the reports thus reducing the need of human labor.

Consistent Operations

The progress report shows consistent improvement management of the operation

Flexibility in designing the process

With the use of Sap, the employees of the organization are able to design the business processes in an innovative manner

Customizing the solution to suit the business process of Yes Chemist

Customization of the business process becomes easier

Reduction in sales and order processing cost

The regular progress reports showing reduction in order processing cost.

Reduced the order delivery time

Customers are getting faster delivery.

However, there are certain dis –benefit of the new system, which are as follows-

  1. In the initial months after the implementation of the project, the productivity might reduce as the employees will need time to understand the working principle of the new system.
  2. The initial cost of development and installation is huge
  3. The hardware design flow of SAP Hana follows a very specific guideline and therefore, it is essential to train the employees in a proper way.
  4. Point in time recovery feature is absent in SAP HANA.

Project Schedule and Approach (Rollout strategy)

The project will include a number of phases. At first, it is very essential to do a proper research on the feasibility of the project. The project will include the different phases of project management which are requirement analysis, implementation, testing and maintenance.

The details about the different phases of the project and the time allocated for each phase is represented in the following table-

Task Name

Duration

Start

Finish

SAP Implementation Project in Yes Chemist

251 days

Fri 01-06-18

Fri 17-05-19

   Project starts

1 day

Fri 01-06-18

Fri 01-06-18

   Feasibility Study

8 days

Mon 04-06-18

Wed 13-06-18

      Operational Feasibility

5 days

Mon 04-06-18

Fri 08-06-18

      Technical Feasibility

6 days

Mon 04-06-18

Mon 11-06-18

      Documenting the report

1 day

Tue 12-06-18

Tue 12-06-18

      Drafting the report

1 day

Wed 13-06-18

Wed 13-06-18

   Requirement Analysis

14 days

Mon 04-06-18

Thu 21-06-18

      Understanding the resource requirements

5 days

Mon 04-06-18

Fri 08-06-18

      Preparation of the project plan

3 days

Mon 11-06-18

Wed 13-06-18

      Obtaining Functional Requirements

4 days

Mon 11-06-18

Thu 14-06-18

      M1: Collection of the functional requirements of the new system design associated with the project

0 days

Thu 14-06-18

Thu 14-06-18

      Preparation of project schedule

3 days

Fri 15-06-18

Tue 19-06-18

      Documenting the reports

2 days

Wed 20-06-18

Thu 21-06-18

   Implementation

102 days

Mon 04-06-18

Tue 23-10-18

      Server room demolition

15 days

Mon 04-06-18

Fri 22-06-18

      Permission for cloud hosting

10 days

Mon 25-06-18

Fri 06-07-18

      M2: Development of Infrastructure and Equipment

0 days

Fri 06-07-18

Fri 06-07-18

      Designing the interface

15 days

Mon 09-07-18

Fri 27-07-18

      Coding the software

30 days

Mon 30-07-18

Fri 07-09-18

      Coding database

30 days

Mon 10-09-18

Fri 19-10-18

      linking the data base with the software

2 days

Mon 22-10-18

Tue 23-10-18

      connection of new servers with the existing network

10 hrs

Mon 25-06-18

Tue 26-06-18

   Data Conversion

22 days

Wed 24-10-18

Thu 22-11-18

      Understanding the legacy of data structures

3 days

Wed 24-10-18

Fri 26-10-18

      Setting up the data extractor and script development

2 days

Mon 29-10-18

Tue 30-10-18

      Data validation and cleansing

3 days

Wed 31-10-18

Fri 02-11-18

      Development of the automated script for loading data into B1 instance

2 days

Mon 05-11-18

Tue 06-11-18

      Testing in real time instance

3 days

Wed 07-11-18

Fri 09-11-18

      Defect rectification

2 days

Mon 12-11-18

Tue 13-11-18

      Post data migration analysis

4 days

Wed 14-11-18

Mon 19-11-18

      Manual data rectification by client

3 days

Tue 20-11-18

Thu 22-11-18

   M3: Successful Data Conversion

0 days

Thu 22-11-18

Thu 22-11-18

   Integration and Testing

35 days

Fri 23-11-18

Thu 10-01-19

      Integration of new SAP system with e-gate feature for corporate banking

5 days

Fri 23-11-18

Thu 29-11-18

      Testing

30 days

Fri 30-11-18

Thu 10-01-19

         unit testing

5 days

Fri 30-11-18

Thu 06-12-18

         system testing

6 days

Fri 07-12-18

Fri 14-12-18

         black box testing

5 days

Fri 07-12-18

Thu 13-12-18

         alpha testing

5 days

Fri 14-12-18

Thu 20-12-18

         end to end testing with live e-gate instance

10 days

Fri 21-12-18

Thu 03-01-19

         System integration Testing

5 days

Fri 04-01-19

Thu 10-01-19

      M4: Completion of Integration and testing of SAP

0 days

Thu 10-01-19

Thu 10-01-19

   Documentation and training

61 days

Fri 04-01-19

Fri 29-03-19

      Documenting the project progress and project reports

7 days

Fri 04-01-19

Mon 14-01-19

      Development of functionality manuals

10 days

Fri 04-01-19

Thu 17-01-19

      Reviewing the standard of SAP business All in one end user manuals

20 days

Fri 18-01-19

Thu 14-02-19

      Customization of the manuals based on client's delivery requirements

10 days

Fri 15-02-19

Thu 28-02-19

      Training by VUISC trainer to the staffs of Yes Chemist

21 days

Fri 01-03-19

Fri 29-03-19

   M5: Completion of Documentation and training Phase

0 days

Fri 29-03-19

Fri 29-03-19

   Acceptance Testing and Client Sign off

15 days

Mon 01-04-19

Fri 19-04-19

      Performing acceptance testing on the application developed

10 days

Mon 01-04-19

Fri 12-04-19

      Sign Off

5 days

Mon 15-04-19

Fri 19-04-19

         Completion of hardware and software installation

2 days

Mon 15-04-19

Tue 16-04-19

         Checking whether data conversion and training is successfully completed

2 days

Mon 15-04-19

Tue 16-04-19

         Documenting the report

5 days

Mon 15-04-19

Fri 19-04-19

   M6: Completion of Acceptance Testing and successful client sign off

0 days

Fri 19-04-19

Fri 19-04-19

   Application go live

20 days

Mon 22-04-19

Fri 17-05-19

      server equipments tested by VUISC technical staff before SAP installation

2 days

Mon 22-04-19

Tue 23-04-19

      Installation by Frontline Engineer

2 days

Wed 24-04-19

Thu 25-04-19

      go live

1 day

Fri 26-04-19

Fri 26-04-19

      Maintenance post go live

3 wks

Mon 29-04-19

Fri 17-05-19

   Project Ends

0 days

Fri 17-05-19

Fri 17-05-19

The work activities marked in red in the Gantt chart above depict the critical path of the project (Larson and Gray 2013)

Resources

The human resources associated with this project is represented below-

Resource Name

Std. Rate

Cost/Use

IT Project Manager VUISC

$75.00/hr

$0.00

VUISC Programmers

$30.00/hr

$0.00

VUISC Testers

$35.00/hr

$0.00

VUISC business Analyst

$50.00/hr

$0.00

VUISC Technical writers

$30.00/hr

$0.00

VUISC End user trainers

$25.00/hr

$0.00

Jacob and Sons Pty Ltd subcontracting staffs

$0.00/hr

$15,000.00

Peter Cables Pty Ltd

$60.00/hr

$0.00

Frontline Engineer

$30.00/hr

$0.00

VUISC technical staffs

$20.00/hr

$0.00

The resource report is represented below-

The above report gives an overview of the resources associated with the project and the responsibilities of each resource. 

Budget

The cost estimated for the project is represented in the following table –

WBS

Task Name

Duration

Cost

0

SAP Implementation Project in Yes Chemist

251 days

$109,845.00

1

   Project starts

1 day

$600.00

2

   Feasibility Study

8 days

$7,000.00

2.1

      Operational Feasibility

5 days

$2,800.00

2.2

      Technical Feasibility

6 days

$3,360.00

2.3

      Documenting the report

1 day

$240.00

2.4

      Drafting the report

1 day

$600.00

3

   Requirement Analysis

14 days

$9,480.00

3.1

      Understanding the resource requirements

5 days

$3,000.00

3.2

      Preparation of the project plan

3 days

$1,800.00

3.3

      Obtaining Functional Requirements

4 days

$2,400.00

3.4

      M1: Collection of the functional requirements of the new system design associated with the project

0 days

$0.00

3.5

      Preparation of project schedule

3 days

$1,800.00

3.6

      Documenting the reports

2 days

$480.00

4

   Implementation

102 days

$40,305.00

4.1

      Server room demolition

15 days

$15,000.00

4.2

      Permission for cloud hosting

10 days

$6,000.00

4.3

      M2: Development of Infrastructure and Equipment

0 days

$0.00

4.4

      Designing the interface

15 days

$3,600.00

4.5

      Coding the software

30 days

$7,200.00

4.6

      Coding database

30 days

$7,200.00

4.7

      linking the data base with the software

2 days

$480.00

4.8

      connection of new servers with the existing network

10 hrs

$825.00

5

   Data Conversion

22 days

$4,760.00

5.1

      Understanding the legacy of data structures

3 days

$480.00

5.2

      Setting up the data extractor and script development

2 days

$320.00

5.3

      Data validation and cleansing

3 days

$480.00

5.4

      Development of the automated script for loading data into B1 instance

2 days

$320.00

5.5

      Testing in real time instance

3 days

$1,320.00

5.6

      Defect rectification

2 days

$480.00

5.7

      Post data migration analysis

4 days

$640.00

5.8

      Manual data rectification by client

3 days

$720.00

6

   M3: Successful Data Conversion

0 days

$0.00

7

   Integration and Testing

35 days

$11,480.00

7.1

      Integration of new SAP system with e-gate feature for corporate banking

5 days

$800.00

7.2

      Testing

30 days

$10,680.00

7.2.1

         unit testing

5 days

$1,400.00

7.2.2

         system testing

6 days

$1,680.00

7.2.3

         black box testing

5 days

$1,400.00

7.2.4

         alpha testing

5 days

$1,400.00

7.2.5

         end to end testing with live e-gate instance

10 days

$2,800.00

7.2.6

         System integration Testing

5 days

$2,000.00

7.3

      M4: Completion of Integration and testing of SAP

0 days

$0.00

8

   Documentation and training

61 days

$18,620.00

8.1

      Documenting the project progress and project reports

7 days

$1,120.00

8.2

      Development of functionality manuals

10 days

$2,400.00

8.3

      Reviewing the standard of SAP business All in one end user manuals

20 days

$8,000.00

8.4

      Customization of the manuals based on client's delivery requirements

10 days

$2,400.00

8.5

      Training by VUISC trainer to the staffs of Yes Chemist

21 days

$4,700.00

9

   M5: Completion of Documentation and training Phase

0 days

$0.00

10

   Acceptance Testing and Client Sign off

15 days

$4,640.00

10.1

      Performing acceptance testing on the application developed

10 days

$2,800.00

10.2

      Sign Off

5 days

$1,840.00

10.2.1

         Completion of hardware and software installation

2 days

$320.00

10.2.2

         Checking whether data conversion and training is successfully completed

2 days

$320.00

10.2.3

         Documenting the report

5 days

$1,200.00

11

   M6: Completion of Acceptance Testing and successful client sign off

0 days

$0.00

12

   Application go live

20 days

$12,960.00

12.1

      server equipments tested by VUISC technical staff before SAP installation

2 days

$320.00

12.2

      Installation by Frontline Engineer

2 days

$480.00

12.3

      go live

1 day

$760.00

12.4

      Maintenance post go live

3 wks

$11,400.00

13

   Project Ends

0 days

$0.00

The following report gives an overview of the resource cost overview associated with the project-

The cost of work is huge since the schedule of the project is long and the project work is quite complex.

Risk

Every project is associated with a certain amount of risk that needs to be properly managed in order to eliminate the chances of project failure (McNeil,  Frey and Embrechts 2015). A risk register is prepared for documenting the different risks that is associated with the SAP implementation project in Yes Chemist. A risk register is a master document that is created in the early stages of the project and is therefore an important part of Risk management plan (Alhawari, S., Karadsheh, Talet and Mansour 2012). A risk register helps in addressing the different risks and problems as they arise.

The risks associated with the SAP implementation are as follows (Galliers and Leidner 2014) –

S.No

Security Threat/Risk Description

Likelihood

Impact

Priority

Preventive Actions

1.

 

Any problem in data conversion  and data transfer might result in the permanent data loss

Medium

High

High

As a preventive action, the data conversion and transfer which is a significant project deliverable should be completed in a controlled environment

2.

 

Technical risk in testing of the developed modules

Medium

High

High

As a mitigation approach, the testing phase is allocated with a considerable times

3.

 

Schedule risk due to delay in the resources availability

Low

Medium

Medium

As a risk mitigation approach, the daily progress of the project is needed to be tracked

4.

 

Operational Risk due to inexperienced employees

High

High

High

The training should be imparted to the maximum number of employees

5.

 

The SAP system is not providing the expected output

Low

High

High

As a risk mitigation approach, proper requirement analysis and research about SAP HANA is to be made prior to its implementation.

6.

 

Project Experiencing frequent delays and slippage in deadline

Medium

Medium

Medium

The project manager should have a clear visibility of the project progress and timely completion of the deliverable.

Communication

Proper communication flow among the team members is essential in measuring the success of the project (Binder 2016). A communication matrix is a tool that is designed to get an overview on how an individual in communicating. The communication matrix for this project in represented in the following table (Martinelli and Milosevic 2016)- 

Communication
activities

Target
Audience

Description/Purpose

Frequency

Distribution
Vehicle

Weekly status report

Project Team

Communicate updated project status

Weekly

email

 Project Progress Report

 Project Team along with project manager

 Communicate the project progress

 In every two weeks

 Email, face to face communication

Delivery or communication of key messages

 The project team

 Any recent development in the project needs to be communicated

 Regularly

 Phone calls

 Impact assessment report

 Project team and stakeholders

 Communicating the impact assessment report

 Bi-weekly

 Email

 Updated schedule

 Project team members

 Communicating any update in schedule

 As required

 Email

Summary

The project plan demonstrates the different phases and activities associated with the project of Yes Chemist. A SAP application will be implemented for integrating all the business processes associated with the organization. The project plan gives an overview of the project scope, business case, schedule, resources and budget, associated risks and the project communication plan.

References 

Alhawari, S., Karadsheh, L., Talet, A.N. and Mansour, E., 2012. Knowledge-based risk management framework for information technology project. International Journal of Information Management, 32(1), pp.50-65.

Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.

Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.

Galliers, R.D. and Leidner, D.E. eds., 2014. Strategic information management: challenges and strategies in managing information systems. Routledge.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Larson, E.W. and Gray, C., 2013. Project management: The managerial process with MS project. McGraw-Hill.

Leach, L.P., 2014. Critical chain project management. Artech House.

Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

McNeil, A.J., Frey, R. and Embrechts, P., 2015. Quantitative risk management: Concepts, techniques and tools. Princeton university press.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.


Buy Bco6656 It Project Management For Assessment Answers Online

Talk to our expert to get the help with Bco6656 It Project Management For Assessment Answers from Assignment Hippo Experts to complete your assessment on time and boost your grades now

The main aim/motive of the finance assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignment help Australia. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at www.assignmenthippo.com are so much skilled, capable, talented, and experienced in their field and use our best and free Citation Generator and cite your writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Bco6656 It Project Management For Assessment Answer Assignment Help Online

Want to order fresh copy of the Sample Bco6656 It Project Management For Assessment Answers? online or do you need the old solutions for Sample Bco6656 It Project Management For Assessment Answer, contact our customer support or talk to us to get the answers of it.

Assignment Help Australia
Want latest solution of this assignment

Want to order fresh copy of the Bco6656 It Project Management For Assessment Answers? online or do you need the old solutions for Sample Bco6656 It Project Management For Assessment Answer, contact our customer support or talk to us to get the answers of it.


); }