Bus375 Management | Launching A Assessment Answer

Answer:

Scope of management plan, including project budget and resources plan

Introduction

The paper mainly focuses on the launch of a new Butcher and steak house restaurant. It is identified that in order to launch the restaurant an event is organized. The main aim of organizing the event is to drive the customer traffic towards the new Butcher and Steak house restaurant so that the restaurant can able to exist in the market by competing with other competitors. It is identified that the event is mainly launched by inviting audience as well as through social media. The main benefits of launching the restaurant include getting attention, enhancing revenue, and advertising brand, enhancing reputation of the restaurant and creating new relationship with the customers. In this paper, proper focus in on the project scope, period of performance, place of performance, work requirements are well ads project milestones.

Scope of Work

The scope of the work is providing below:

  • Launching new Butcher and steak house restaurant
  • Decorating restaurant
  • Hiring chefs
  • Selecting food menu
  • Printing invitation card
  • Give Out Invitations to Special Guests
  • Prepare Special Menu for Launch Day
  • Serve Guests with Special Dishes at Discounted Price
  • Present Guests with Souvenirs
  • Promoting through social media
  • Promote Event in Digital Media

Period of Performance

It is identified that the launch of a new Butcher and steak house restaurant will be successfully completed within the timeframe of 63 days by assuming that the project will commence on 23rd May 2018.  The entire period of performance for each of the activities are provided in the table below:

Place of Performance

The restaurant organizes the event in the new Butcher and Steak House Restaurant so that they can be customers can be able to know about the location and the services that are provided by the restaurant.

Work Requirements

The work requirements of the project are listed in the table below:

WBS

Task Name

0

Launching a new Butcher and Steak House Restaurant

1

   Project planning phase

1.1

      Development of event plan

1.1.1

         Resources needed for the event

1.1.2

         Financial plan for the event

1.2

      Developing quality management plan for the event

1.2.1

         Checking quality of the raw materials

1.2.2

          Analyzing risks that affects project quality

1.3

      Communication plan

1.3.1

          Communication roles

1.3.2

         Communication tools and methods

2

   Initiation phase

2.1

      Preparing launching plan

2.1.1

          Involvement of top management

2.1.2

         Identifying the need of launching business

2.2

      Feasibility study

2.2.1

         Undertaking cost benefit analysis

2.2.2

          Undertaking feasibility of the project

2.3

      Establishing project charter

2.3.1

         Appointing team members

2.3.2

          Identifying people needed

3

   Making arrangements

3.1

      Determining target audience

3.1.1

         Determining the audience that are needed to be targeted

3.1.2


         Identifying the requirements of the audience

3.2

       Making arrangements

3.2.1

         Decorating restaurant

3.2.2

         Hiring chefs

3.2.3

          Selecting food menu

3.3

      Inviting audiences

3.3.1

          Printing invitation card

3.3.2

         Give Out Invitations to Special Guests

3.3.3

         Prepare Special Menu for Launch Day

4

   Executing the event

4.1

      Starting event

4.1.1

         Grand Opening

4.1.2

         Serve Guests with Special Dishes at Discounted Price

4.1.3

         Present Guests with Souvenirs

4.2

      Event promotion

4.2.1

         Promoting through social media

4.2.2

         Promote Event in Digital Media

4.2.3

         Release Special Offers for Event

4.3

      Closure

4.3.1

         Closing the event

Milestone/schedules

The schedule of the project is provided in the table below:

Task Name

Duration

Start

Finish

Launching a new Butcher and Steak House Restaurant

61 days

Wed 23-05-18

Wed 15-08-18

   Project planning phase

11 days

Wed 23-05-18

Wed 06-06-18

      Development of event plan

3 days

Wed 23-05-18

Fri 25-05-18

         Resources needed for the event

2 days

Wed 23-05-18

Thu 24-05-18

         Financial plan for the event

1 day

Fri 25-05-18

Fri 25-05-18

      Developing quality management plan for the event

4 days

Mon 28-05-18

Thu 31-05-18

         Checking quality of the raw materials

2 days

Mon 28-05-18

Tue 29-05-18

          Analyzing risks that affects project quality

2 days

Wed 30-05-18

Thu 31-05-18

      Communication plan

4 days

Fri 01-06-18

Wed 06-06-18

          Communication roles

2 days

Fri 01-06-18

Mon 04-06-18

         Communication tools and methods

2 days

Tue 05-06-18

Wed 06-06-18

   Initiation phase

18 days

Thu 07-06-18

Mon 02-07-18

      Preparing launching plan

5 days

Thu 07-06-18

Wed 13-06-18

          Involvement of top management

3 days

Thu 07-06-18

Mon 11-06-18

         Identifying the need of launching business

2 days

Tue 12-06-18

Wed 13-06-18

      Feasibility study

6 days

Thu 14-06-18

Thu 21-06-18

         Undertaking cost benefit analysis

3 days

Thu 14-06-18

Mon 18-06-18

          Undertaking feasibility of the project

3 days

Tue 19-06-18

Thu 21-06-18

      Establishing project charter

7 days

Fri 22-06-18

Mon 02-07-18

         Appointing team members

3 days

Thu 28-06-18

Mon 02-07-18

          Identifying people needed

4 days

Fri 22-06-18

Wed 27-06-18

   Making arrangements

19 days

Tue 03-07-18

Fri 27-07-18

      Determining target audience

5 days

Tue 03-07-18

Mon 09-07-18

         Determining the audience that are needed to be targeted

3 days

Tue 03-07-18

Thu 05-07-18

         Identifying the requirements of the audience

2 days

Fri 06-07-18

Mon 09-07-18

       Making arrangements

9 days

Tue 10-07-18

Fri 20-07-18

         Decorating restaurant

3 days

Tue 10-07-18

Thu 12-07-18

         Hiring chefs

4 days

Fri 13-07-18

Wed 18-07-18

          Selecting food menu

2 days

Thu 19-07-18

Fri 20-07-18

      Inviting audiences

5 days

Mon 23-07-18

Fri 27-07-18

          Printing invitation card

2 days

Mon 23-07-18

Tue 24-07-18

         Give Out Invitations to Special Guests

2 days

Wed 25-07-18

Thu 26-07-18

         Prepare Special Menu for Launch Day

1 day

Fri 27-07-18

Fri 27-07-18

   Executing the event

13 days

Mon 30-07-18

Wed 15-08-18

      Starting event

5 days

Mon 30-07-18

Fri 03-08-18

         Grand Opening

1 day

Mon 30-07-18

Mon 30-07-18

         Serve Guests with Special Dishes at Discounted Price

2 days

Tue 31-07-18

Wed 01-08-18

         Present Guests with Souvenirs

2 days

Thu 02-08-18

Fri 03-08-18

      Event promotion

7 days

Mon 06-08-18

Tue 14-08-18

         Promoting through social media

2 days

Mon 06-08-18

Tue 07-08-18

         Promote Event in Digital Media

2 days

Wed 08-08-18

Thu 09-08-18

         Release Special Offers for Event

3 days

Fri 10-08-18

Tue 14-08-18

      Closure

1 day

Wed 15-08-18

Wed 15-08-18

         Closing the event

1 day

Wed 15-08-18

Wed 15-08-18

Budget

 It is estimated that the budget that is needed for launching a new Butcher and Steak House Restaurant will be around $38,400. The budget that is needed for executing each activities are listed below:

Task Name

Duration

Cost

Launching a new Butcher and Steak House Restaurant

61 days

$ 38,400.00

   Project planning phase

11 days

$ 12,920.00

      Development of event plan

3 days

$ 10,280.00

         Resources needed for the event

2 days

$ 10,000.00

         Financial plan for the event

1 day

$ 280.00

      Developing quality management plan for the event

4 days

$ 1,120.00

         Checking quality of the raw materials

2 days

$ 560.00

          Analyzing risks that affects project quality

2 days

$ 560.00

      Communication plan

4 days

$ 1,520.00

          Communication roles

2 days

$ 880.00

         Communication tools and methods

2 days

$ 640.00

   Initiation phase

18 days

$ 6,720.00

      Preparing launching plan

5 days

$ 1,960.00

          Involvement of top management

3 days

$ 1,320.00

         Identifying the need of launching business

2 days

$ 640.00

      Feasibility study

6 days

$ 1,800.00

         Undertaking cost benefit analysis

3 days

$ 840.00

          Undertaking feasibility of the project

3 days

$ 960.00

      Establishing project charter

7 days

$ 2,960.00

         Appointing team members

3 days

$ 1,200.00

          Identifying people needed

4 days

$ 1,760.00

   Making arrangements

19 days

$ 6,720.00

      Determining target audience

5 days

$ 1,720.00

         Determining the audience that are needed to be targeted

3 days

$ 840.00

         Identifying the requirements of the audience

2 days

$ 880.00

       Making arrangements

9 days

$ 3,240.00

         Decorating restaurant

3 days

$ 840.00

         Hiring chefs

4 days

$ 1,760.00

          Selecting food menu

2 days

$ 640.00

      Inviting audiences

5 days

$ 1,760.00

          Printing invitation card

2 days

$ 800.00

         Give Out Invitations to Special Guests

2 days

$ 640.00

         Prepare Special Menu for Launch Day

1 day

$ 320.00

   Executing the event

13 days

$ 12,040.00

      Starting event

5 days

$ 1,760.00

         Grand Opening

1 day

$ 400.00

         Serve Guests with Special Dishes at Discounted Price

2 days

$ 560.00

         Present Guests with Souvenirs

2 days

$ 800.00

      Event promotion

7 days

$ 9,840.00

         Promoting through social media

2 days

$ 8,000.00

         Promote Event in Digital Media

2 days

$ 640.00

         Release Special Offers for Event

3 days

$ 1,200.00

      Closure

1 day

$ 440.00

         Closing the event

1 day

$ 440.00

Resource Plan

Resource Name

Type

Max. Units

Std. Rate

Cost/Use

Accrue At

Base Calendar

Event planner

Work

100%

$ 50.00/hr.

$ 0.00

Prorated

Standard

Organizer

Work

100%

$ 40.00/hr.

$ 0.00

Prorated

Standard

Financial manager

Work

100%

$ 35.00/hr.

$ 0.00

Prorated

Standard

Quality analyst

Work

100%

$ 35.00/hr.

$ 0.00

Prorated

Standard

Event manager

Work

100%

$ 55.00/hr.

$ 0.00

Prorated

Standard

Chef

Work

100%

$ 40.00/hr.

$ 0.00

Prorated

Standard

Raw materials

Material

 

$ 10,000.00

$ 0.00

Prorated

 

Additional cost

Material

 

$ 8,000.00

$ 0.00

Prorated

 

Volunteer

Work

100%

$ 35.00/hr.

$ 0.00

Prorated

Standard

Acceptance Criteria

It is identified that after the launching of the restaurant all the deliverables of the project mainly reside with the Vice president of marketing. It is identified that the VP of marketing generally helps in maintaining small team of three advisors for making sure that the entire event is successfully completed by meeting the objectives and scope of the project. It is identified that after the launching of the restaurant, the restaurant can be able to provide proper services to the customers of the organization.

Other requirements

The Launching of new Butcher and Steak House Restaurant must be advertised so that more customers can visit the restaurant, which further helps in enhancing the revenue of the restaurant.

Acceptance

Approved by:

Date:

<Approvers Name>

<Approvers Title>

Work breakdown structure

Figure 1: WBS

(Source: Created by Author)

Stakeholder management plan

Roles and responsibilities

Name

Role

Responsibility

<Please Fill>

 Event planner

·  The event planner will create proper plan in order to launch the Butcher and Steak House Restaurant

<Please Fill>

 Organizer

·  They are generally responsible for restructuring the team and assigns them tasks for completing the tasks and duties for launching Butcher and Steak House Restaurant

<Please Fill>

Financial manager

·  They are generally responsible for reviewing various types of financial reports and assist in preparing activity reports.

<Please Fill>

 Quality analyst

·  Quality analyst will generally engages in developing test plans for identifying the quality of the project.

<Please Fill>

Event manager

·  The event manager is responsible for arranging for the project so that the restaurant can be launched successfully.

<Please Fill>

Chef

·  The Chef arranges for the food so that proper food service is provided to the customers.

<Please Fill>

Volunteers

·  The volunteers engage in managing the work activities that are required to be done for website launch.

Stakeholder analysis

Stakeholders

Influence

Impact

 Event planner

 High

High

 Organizer

Low

High

Financial manager

Low

High

 Quality analyst

Low

High

Event manager

High

High

Chef

Low

High

Volunteers

Low

High

Stakeholder management strategies

Name, position, etc.

Interest

Message

Communication Channel

Frequency

 Event planner

Objectives and project scope

The messages must be related with achieving project goals and objectives.

Face to face

Once

 Organizer

 Inform about the status of the event

 The project is on track

Face to face, conference

Weekly

Financial manager

 About the project budget

Informs whether the project is on track or not

Face to face, conference

Monthly

 Quality analyst

Informs about quality

 Analyzes  whether the event meet the objectives of the restaurant or not

Face to face

Weekly

Risk management plan

 Risk

Evaluation

 Impact

Probability

Responsible person

Mitigation strategies

Improper slippage

 Due to inappropriate tracking, the event manager faces difficulty in finishing the project.

Very High

Very High

Event planner

Proper tracing of schedule on weekly basis can mitigate this issue.

Inappropriate arrangement

 Due to improper management it is quite difficult to organize the event

High

Medium

 

organizer

It is very much essential to organize the event successfully.

Lack of budget

If the budget of the project is not properly assumed then it can create lot of financial issues.

 Very High

High

Financial manager

It is quite essential to estimate the budget quite effectively undertaking proper market analysis.

Inexperienced event managers

If the event manager are less experienced then can face difficulty in

launching a new Butcher and Steak House Restaurant

Medium

Medium

Event manager

It is very much necessary to hire experienced event managers

 

Probability

Very high

 

 

 

Lack of budget

Improper slippage

High

 

 

Inappropriate arrangement

 

 

Medium

 

 

Inexperienced event managers

 

 

Low

 

 

 

 

 

Very low

 

 

 

 

 

 

Very low

Low

Medium

High

Very high

 

Impact

Event evaluation

It is identified that the event was mainly undertaken in order to launch new Butcher and Steak House Restaurant. As per the project planning, it is reflected that the website launching will be finished within the duration that is around 61 days by utilizing budget of around $38,400. The launching of the restaurant will be helpful in targeting the audience and it assists in providing an opportunity to the restaurant to drive the traffic of the audiences. Furthermore, it is identified that there are number of risks that are associated with the event that need to be mitigated by taking proper steps.

References

Andersen, E. S. (2016). Do project managers have different perspectives on project management?. International Journal of Project Management, 34(1), 58-65.

Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques. A theoretical framework. Journal of Risk Research, 18(2), 232-248.

Fernandes, G., Ward, S., & Araújo, M. (2015). Improving and embedding project management practice in organisations—A qualitative study. International Journal of Project Management, 33(5), 1052-1067.

Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC Press, LLC.

Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence.pearson.

Hegazy, T. (2013). Computer-Based Construction Project Management: Pearson New International Edition. Pearson Higher Ed.

Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley & Sons.

Hubicki, M. (2014). Risk Management Plan.

Hwang, B. G., & Ng, W. J. (2013). Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), 272-284.

Kami, N. (2015). U.S. Patent No. 9,116,916. Washington, DC: U.S. Patent and Trademark Office.

Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.

Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Larson, E. W., &Gray, C. (2013). Project Management: The Managerial Process with MS Project. McGraw-Hill.

Mir, F. A., &Pinnington, A. H. (2014).Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Nanda, V. (2016). Quality management system handbook for product development companies.CRC Press.

Pemsel, S., &Wiewiora, A. (2013).Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31-42.

Stark, J. (2015). Product lifecycle management.In Product Lifecycle Management (pp. 1-29).Springer International Publishing.

Todorovi?, M. L., Petrovi?, D. ?., Mihi?, M. M., Obradovi?, V. L., &Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.

Tornabene, C., Hussain, M. M., Crowe, T., Cohen, N., & Panzer, J. (2012).U.S. Patent No. 8,103,729. Washington, DC: U.S. Patent and Trademark Office.

Verburg, R. M., Bosch-Sijtsema, P., &Vartiainen, M. (2013).Getting it done: Critical success factors for project managers in virtual work settings.International Journal of Project Management, 31(1), 68-79.


Buy Bus375 Management | Launching A Assessment Answers Online

Talk to our expert to get the help with Bus375 Management | Launching A Assessment Answers from Assignment Hippo Experts to complete your assessment on time and boost your grades now

The main aim/motive of the finance assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignment help Australia. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at www.assignmenthippo.com are so much skilled, capable, talented, and experienced in their field and use our best and free Citation Generator and cite your writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Bus375 Management | Launching A Assessment Answer Assignment Help Online

Want to order fresh copy of the Sample Bus375 Management | Launching A Assessment Answers? online or do you need the old solutions for Sample Bus375 Management | Launching A Assessment Answer, contact our customer support or talk to us to get the answers of it.

Assignment Help Australia
Want latest solution of this assignment

Want to order fresh copy of the Bus375 Management | Launching A Assessment Answers? online or do you need the old solutions for Sample Bus375 Management | Launching A Assessment Answer, contact our customer support or talk to us to get the answers of it.