Ict352 Data And Information Answers Assessment Answer

Answer:

The aim of this report is to evaluate the existing system of the TOSIG (Tier One Suppliers Insurance Company) and propose the cloud computing as the appropriate approach for the management of the new customers. The identified problem was that the agents were not able to retrieve data while communicating with new customers outside the office premises and that led to the less influence on the customers to be associate with the organization. Cloud computing will allow the agents to be connected with the data and information 24*7 hours and thus, improve the figures of the new customers associating with the organization.

1.2 Objectives

  • To establish a cloud computing network for the agents of the TOSIG
  • To migrate the data over the cloud
  • To increase the number of new customers
  • To analyze the feasibility of the cloud computing as the solution for the identified problem
  • To automate the manual system and eliminate the human errors

1.3 Budget Estimate and Assumptions

            The feasibility study can be done with a budget of $ 10,000 however; the entire project can be delivered with a budget of $ 50,000 as expressed in this report.

1.3.1 Assumptions

Following are the assumptions:

  • The project will be approved by the executives
  • The timeline and cost of the budget will not be altered
  • There will be appropriate sponsors
  • The employees will not resist the new transformation
  • The conflicts will be managed in an efficient and effective manner

1.3.2 Project Name

Name of the project will be Transformation in TOSIG

1.3.3 Time:

The expected time for the project will be less than seven months

2. Business case

2.1 Roles and Responsibilities

Stakeholder

Name

Roles

Responsibilities

Organization executives

Tahlia McWilliams

Take hard decisions on sensitive transformations

Take decisions considering every stakeholder

Project Manager

Archer Polglaze

Manage the project activities and stakeholders

Maintain the project constraints

Business Analyst

Gabriella Dunbabin

Analyze the needs and requirements of the business

Comply the solution with the business requirements

Market analyst

Nathan Liston

Analyze the competitors status

Propose a sophisticated data analysis

Resource Manager

Leah Nairn

Manage the resources for the delivery of the project

Make sure that there is neither lack in resources or excess in resources

Cloud Vendors

Microsoft Azure

Provide cloud services

Comply the TOSIG’s policy with theirs

IT technicians

Liam Learmonth

Manage the technical jobs

Make sure that the system does not have any bugs or glitches

HR

Jacob Macarthur-Onslow

Manage the human resources

To aware the human resources about their rights

Finance Manager

Gabriel Hetherington

Manage the financial status of the project

Make sure that the financial related requirements are fulfilled

The agents are facing trouble in presenting the overall information in front of the customers that is not helping in engaging them with the organization and take insurance from the company. The agents are not able to access the data and information on the field and hence, not able to attract customers so, cloud implementation within the existing system will be helpful in eliminating this issue and providing the agents with a facility to access the data and information on the fields. This transformation will not need the data migration over the cloud rather the organization will also need to utilize on-demand software services and providing the agents with the mobile devices those are compatible with the new applications.

3.1 Tools and Techniques

            SAP ERP, Microsoft AZURE, IT infrastructure, High bandwidth internet connection, latest mobile devices with better configuration, and wireless connectivity are the tools those are necessary for the successful deployment of this project.

4. Stakeholder Analysis

4.1 Stakeholder Register


SL No

Stakeholder

Interest

Impact

1

Organization executives

Very high

Very High

2

Project Manager

High

Very High

3

Business Analyst

Medium

High

4

Market analyst

Medium

Medium

5

Resource Manager

Low

High

6

Cloud Vendors

Very High

Very Low

7

IT technicians

Low

Low

8

HR

Medium

Low

9

Finance Manager

Very Low

Low

10

Customers

Very Low

Very Low

11

Agents

Very High

High

4.2 Stakeholder Prioritization Matrix

Interest

 

 

 

 

 

Very High

6

 

 

11

1

High

 

 

 

 

2

Medium

 

8

4

3

 

Low

 

7

 

5

 

Very low

10

9

 

 

 

Impact

Very Low

Low

Medium

High

Very High

5. Milestone Schedule

Milestones:

Task Name

Duration

Start

Finish

TOSIG migration to cloud

192 days

Mon 5/28/18

Tue 2/19/19

   Project Planning

42 days

Mon 5/28/18

Tue 7/24/18

      Milestone 1: Planning completed

0 days

Tue 7/24/18

Tue 7/24/18

   New platform preparation

38 days

Wed 7/25/18

Fri 9/14/18

      Milestone 2: New platform preparation completed

0 days

Fri 9/14/18

Fri 9/14/18

   Import services routine

52 days

Fri 11/2/18

Mon 1/14/19

      Evaluation of new clients

3 days

Thu 1/10/19

Mon 1/14/19

         Milestone 4: Importing Data completed

0 days

Mon 1/14/19

Mon 1/14/19

   Project closure

26 days

Tue 1/15/19

Tue 2/19/19

      Milestone 5: project Hand over completed

0 days

Tue 2/19/19

Tue 2/19/19


Schedule and Budget

WBS

Task Name

Duration

Start

Finish

Resource Names

Cost

1

TOSIG migration to cloud

192 days

Mon 5/28/18

Tue 2/19/19

 

$47,224.00

1.1

Project Planning

42 days

Mon 5/28/18

Tue 7/24/18

 

$12,880.00

1.1.1

Defining project objectives

2 days

Mon 5/28/18

Tue 5/29/18

Business analyst, Market analyst, Project Manager, System Analyst

$800.00

1.1.2

Estimating Milestones

3 days

Wed 5/30/18

Fri 6/1/18

Business analyst, Market analyst, Project Manager, System Analyst

$1,200.00

1.1.3

Developing migration plan

2 days

Mon 6/4/18

Tue 6/5/18

 

$480.00

1.1.3.1

Defining Methods

2 days

Mon 6/4/18

Tue 6/5/18

Business analyst, Market analyst, System Analyst

$480.00

1.1.4

Defining Audit control requirements

2 days

Wed 6/6/18

Thu 6/7/18

Business analyst, Market analyst, System Analyst, Finance Manager, Project Manager

$880.00

1.1.5

Quality Management plan definition

9 days

Fri 6/8/18

Wed 6/20/18

 

$2,160.00

1.1.5.1

Defining the risks

3 days

Fri 6/8/18

Tue 6/12/18

Finance Manager, Market analyst, Resource Manager, TOSIG Executive

$600.00

1.1.5.2

Defying the plans for testing

3 days

Wed 6/13/18

Fri 6/15/18

Business analyst, Market analyst, System Analyst

$720.00

1.1.5.3

Defining rollback plan

3 days

Mon 6/18/18

Wed 6/20/18

Business analyst, Cloud Service Provider, Resource Manager, System Analyst

$840.00

1.1.6

Defining system run

4 days

Thu 6/21/18

Tue 6/26/18

Business analyst, Finance Manager, Project Manager, Resource Manager, System Analyst

$1,760.00

1.1.7

Estimating budget of the project

4 days

Wed 6/27/18

Mon 7/2/18

Finance Manager, Project Manager, Resource Manager

$1,120.00

1.1.8

HR planning

6 days

Tue 7/3/18

Tue 7/10/18

Finance Manager, Project Manager, Resource Manager

$1,680.00

1.1.9

Executing Kick-off meeting

10 days

Wed 7/11/18

Tue 7/24/18

Finance Manager, Project Manager, Resource Manager

$2,800.00

1.1.10

Milestone 1: Planning completed

0 days

Tue 7/24/18

Tue 7/24/18

 

$0.00

1.2

New platform preparation

38 days

Wed 7/25/18

Fri 9/14/18

 

$7,828.00

1.2.1

Acquiring API

5 days

Wed 7/25/18

Tue 7/31/18

IT technician, Programmer, Software[1], System Analyst

$780.00

1.2.2

Reviewing API

4 days

Wed 8/1/18

Mon 8/6/18

IT technician, Programmer, Software[1], System Analyst, Cloud Service Provider

$804.00

1.2.3

reviewing the existing system

6 days

Tue 8/7/18

Tue 8/14/18

IT technician, Programmer, Software[1], System Analyst

$916.00

1.2.4

New customer relationship system

2 days

Wed 8/15/18

Thu 8/16/18

IT technician, Programmer, Software[1], System Analyst, Business analyst, Market analyst

$692.00

1.2.5

Customer preferences identification

5 days

Fri 8/17/18

Thu 8/23/18

IT technician, Programmer, Software[1], System Analyst, Business analyst, Market analyst

$1,580.00

1.2.6

Data migration

3 days

Fri 8/24/18

Tue 8/28/18

IT technician, Programmer, Software[1], System Analyst, Business analyst, Market analyst

$988.00

1.2.7

Documenting detailed requirements

7 days

Wed 8/29/18

Thu 9/6/18

IT technician, Programmer, Software[1], System Analyst

$1,052.00

1.2.8

Defining the business rules

2 days

Fri 9/7/18

Mon 9/10/18

IT technician, Programmer, Software[1], System Analyst

$372.00

1.2.9

System Configuration

4 days

Tue 9/11/18

Fri 9/14/18

IT technician, Programmer, Software[1], System Analyst

$644.00

1.2.10

Milestone 2: New platform preparation completed

0 days

Fri 9/14/18

Fri 9/14/18

 

$0.00

1.3

Existing platform and devices identification

34 days

Mon 9/17/18

Thu 11/1/18

 

$10,088.00

1.3.1

Analysing the specification of the devices

6 days

Mon 9/17/18

Mon 9/24/18

Business analyst, Cloud Service Provider, Finance Manager, Hardware[1], IT technician, Project Manager, Resource Manager, Software[1], System Analyst, TOSIG Executive

$3,272.00

1.3.2

distributing new mobile devices

8 days

Tue 9/25/18

Thu 10/4/18

Business analyst, Cloud Service Provider, Finance Manager, Hardware[1], IT technician, Project Manager, Resource Manager, Software[1], System Analyst, TOSIG Executive

$4,296.00

1.3.3

task review and quality assurance

20 days

Fri 10/5/18

Thu 11/1/18

 

$2,520.00

1.3.3.1

evaluating the data exports

6 days

Fri 10/5/18

Fri 10/12/18

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1]

$776.00

1.3.3.2

Analysing growth in the new customers' list

5 days

Mon 10/15/18

Fri 10/19/18

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1]

$680.00

1.3.3.3

Milestone 3: Analysis of existing platform completed

9 days

Mon 10/22/18

Thu 11/1/18

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1]

$1,064.00

1.4

Import services routine

52 days

Fri 11/2/18

Mon 1/14/19

 

$10,852.00

1.4.1

Mapping trial data to API

7 days

Fri 11/2/18

Mon 11/12/18

IT technician, Programmer, System Analyst

$952.00

1.4.2

Building routines

4 days

Tue 11/13/18

Fri 11/16/18

IT technician, Programmer, System Analyst, Hardware[1], Software[1]

$744.00

1.4.3

Testing Routines

5 days

Mon 11/19/18

Fri 11/23/18

IT technician, Programmer, System Analyst, Hardware[1], Software[1]

$880.00

1.4.4

Confirming Data Compliance

8 days

Mon 11/26/18

Wed 12/5/18

IT technician, Programmer, System Analyst

$1,088.00

1.4.5

Data import

5 days

Thu 12/6/18

Wed 12/12/18

Cloud Service Provider, Hardware[1], Software[1]

$400.00

1.4.6

Quality Assurance

20 days

Thu 12/13/18

Wed 1/9/19

 

$5,948.00

1.4.6.1

Staff Scheduling

6 days

Thu 12/13/18

Thu 12/20/18

Project Manager, Resource Manager, TOSIG Executive

$1,440.00

1.4.6.2

Testing schedules

7 days

Fri 12/21/18

Mon 12/31/18

Project Manager, Resource Manager, TOSIG Executive, IT technician, Programmer, Software[1]

$2,172.00

1.4.6.3

Test results review

4 days

Tue 1/1/19

Fri 1/4/19

Project Manager, Resource Manager, TOSIG Executive, System Analyst

$1,280.00

1.4.6.4

Testing documentation

3 days

Mon 1/7/19

Wed 1/9/19

Project Manager, Resource Manager, TOSIG Executive, Business analyst, IT technician

$1,056.00

1.4.7

Evaluation of new clients

3 days

Thu 1/10/19

Mon 1/14/19

 

$840.00

1.4.7.1

Reviewing QA

3 days

Thu 1/10/19

Mon 1/14/19

Finance Manager, Project Manager, System Analyst

$840.00

1.4.7.2

Milestone 4: Importing Data completed

0 days

Mon 1/14/19

Mon 1/14/19

Finance Manager, Project Manager, System Analyst

$0.00

1.5

Project closure

26 days

Tue 1/15/19

Tue 2/19/19

 

$5,576.00

1.5.1

Bugs and glitches fixing process definition

5 days

Tue 1/15/19

Mon 1/21/19

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst

$1,080.00

1.5.2

patching and maintaining schedule

5 days

Tue 1/22/19

Mon 1/28/19

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst

$1,080.00

1.5.3

Documentation

6 days

Tue 1/29/19

Tue 2/5/19

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst

$1,256.00

1.5.4

Manual Data Fixing

4 days

Wed 2/6/19

Mon 2/11/19

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst

$904.00

1.5.5

Project Hand Over

6 days

Tue 2/12/19

Tue 2/19/19

Cloud Service Provider, Hardware[1], IT technician, Programmer, Software[1], System Analyst

$1,256.00

1.5.6

Milestone 5: project Hand over completed

0 days

Tue 2/19/19

Tue 2/19/19

 

$0.00

 5.2 Risk Cause and its Effect

Category

Risk

Potential Cause(s)

Potential Response(s)

Response Strategy

Design

Infeasible design

Waste of time and money

Considering the needs and requirements while designing

Exploit

Resources and team

Ineffective training

Difficult quality trainings

Better trainer and staffs

Accept

Change management

Conflict among stakeholders

Change request might came into light

Proper and effective communication

Reduce

Cost management

Project delivery can be costly

Schedule escalation and improper estimation

Effective cost management

Avoid

Scope

Improper estimation

Improper planning

Proper business case

Reduce

 5.2.1 Problem

  • Resistance from the agents
  • Lack of resources
  • Conflict
  • Data security
  • Compliance with cloud service provider’s policy

5.2.2 Constraints

  • Time: 192 days
  • Budget: $ 47, 224
  • Proposed solution will eliminate all the existing problems
  • Milestones will be accomplishment within assumptions

Conclusion

            The proposed solution will allow TOSIG to effectively manage the new customers and following the project plan proposed in this report will be helpful in developing the project within the expected schedule and time. The proposed solution will be helpful in managing the project constraints and delivering the necessary outcomes and enhancing the performance of the organization.

Bibliography

Binder, J., 2016. Global project management: communication, collaboration and management across borders. Routledge.

Boud, D., Cohen, R. and Sampson, J. eds., 2014. Peer learning in higher education: Learning from and with each other. Routledge.

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.

Heagney, J., 2016. Fundamentals of project management. AMACOM Div American Mgmt Assn.

Joseph. Phillips, P.M.P., Cbap, I. And Pmp, C., 2018. Pmp Project Management Professional Study Guide. Mcgraw-Hill Education.

Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.

Leach, L.P., 2014. Critical chain project management. Artech House.

Meredith, J.R., Shafer, S.M., Mantel Jr, S.J. and Sutton, M.M., 2016. Project management in practice. Wiley Global Education.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Turner, R., 2016. Gower handbook of project management. Routledge.

Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.

Walker, A., 2015. Project management in construction. John Wiley & Sons.



Buy Ict352 Data And Information Answers Assessment Answers Online

Talk to our expert to get the help with Ict352 Data And Information Answers Assessment Answers from Assignment Hippo Experts to complete your assessment on time and boost your grades now

The main aim/motive of the finance assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignment help Australia. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at www.assignmenthippo.com are so much skilled, capable, talented, and experienced in their field and use our best and free Citation Generator and cite your writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Ict352 Data And Information Answers Assessment Answer Assignment Help Online

Want to order fresh copy of the Sample Ict352 Data And Information Answers Assessment Answers? online or do you need the old solutions for Sample Ict352 Data And Information Answers Assessment Answer, contact our customer support or talk to us to get the answers of it.

Assignment Help Australia
Want latest solution of this assignment

Want to order fresh copy of the Ict352 Data And Information Answers Assessment Answers? online or do you need the old solutions for Sample Ict352 Data And Information Answers Assessment Answer, contact our customer support or talk to us to get the answers of it.